Circular No :

Our Ref

:

Date

:

URA/PB/2019/18-CUDG DC/ADMIN/CIRCULAR/PB_19 27 November 2019

CIRCULAR TO PROFESSIONAL INSTITUTES
Who should know Developers, building owners, architects and engineers
Effective Date With immediate effect

UPDATED URBAN DESIGN GUIDELINES AND PLANS FOR URBAN DESIGN AREAS
1. As part of the Master Plan 2019 gazette, URA has updated the urban design guidelines and plans applicable to all Urban Design Areas as listed below: a. Downtown Core b. Marina South c. Museum d. Newton e. Orchard f. Outram g. River Valley h. Singapore River i. Jurong Gateway j. Paya Lebar Central k. Punggol Digital District l. Woodlands Central
2. Guidelines specific to each planning area have been merged into a single set of guidelines for easy reference. To improve the user-friendliness of our guidelines and plans, a map-based version of the urban design guide plans is now available on URA SPACE (Service Portal and Community eServices).
3. All new developments, redevelopments and existing buildings undergoing major or minor refurbishment are required to comply with the updated guidelines.
4. The urban design guidelines provide an overview of the general requirements for developments in the respective Urban Design Areas. For specific sites, additional guidelines may be issued where necessary. The guidelines included herewith do not supersede the detailed guidelines issued, nor the approved plans for developments for specific sites.

5. I would appreciate it if you could convey the contents of this circular to the relevant members of your organisation. You are advised to refer to the Development Control Handbooks and URA’s website for updated guidelines instead of referring to past circulars.
6. For other information on the master plan, urban design guidelines, private property use and approval, car park locations and availability, private residential property transactions, and conservation areas and buildings, use URA SPACE (Service Portal and Community e-Services). This is an online portal packed with useful data and visualisation to help building professionals, business operators and the general public in their decisionmaking. It consolidates detailed information on land use and private property into a one-stop platform presented on geospatial maps. For feedback or enquiries on this circular, please email us.
Thank you.
CHOU MEI (MS) GROUP DIRECTOR (CONSERVATION & URBAN DESIGN) for CHIEF EXECUTIVE OFFICER URBAN REDEVELOPMENT AUTHORITY
YAP LAY BEE (MS) GROUP DIRECTOR (ARCHITECTURE & URBAN DESIGN) for CHIEF EXECUTIVE OFFICER URBAN REDEVELOPMENT AUTHORITY
Join URA's mailing list to get the latest updates on current and future plans and developments around Singapore. Click here to subscribe.

Circular No: URA/PB/2019/18-CUDG

URBAN DESIGN GUIDELINES (UDG) FOR JURONG GATEWAY (JURONG LAKE DISTRICT)

About Jurong Gateway
Jurong Gateway will be the commercial hub of Jurong Lake District (JLD) and the West Region. Occupying a total area of 360 ha, JLD will be the largest commercial centre outside the city centre. The District is intended to cater to the diverse needs of businesses and to create job opportunities closer to where people live. Set amid lush greenery and a huge waterbody, JLD is envisaged to be an attractive lakeside destination for business and leisure. JLD will have two unique but complementary precincts: Jurong Gateway and Lakeside.
Centred around Jurong East MRT interchange station, the 70 ha Jurong Gateway will offer an excellent mix of office, retail and other complementary uses. Refer Appendix 1: Boundary Plan.
Jurong Gateway and Lakeside will be seamlessly integrated. Pedestrians can walk conveniently in all-weather comfort from the Jurong East MRT interchange station and bus interchange to most developments and public facilities in Jurong Gateway and Lakeside through an extensive network of at-grade pedestrian walkways, landscaped malls and elevated pedestrian walkways (J-Walk).
JLD will be developed as an urban model of sustainability and will push the boundaries of design and construction to incorporate sustainability from the onset, adopt new mobility solutions that place less reliance on private vehicles and create delightful spaces through creative placemaking. Underpinning these efforts will be a focus on sustainable development and resource optimisation, as well as the widespread use of smart technologies across the district.
JLD will be a ‘living lab’ and regulatory sandbox to explore new ideas and collaboration models in better planning and designing our city, as well as achieving more ambitious sustainability targets.
This set of guidelines aims to guide the physical development of the area to ensure that individual buildings contribute to, and strengthen the planning vision for the area and create an attractive and pedestrian-friendly physical environment.
Gazetted monuments and conserved buildings are subject to specific conservation guidelines, which will take precedence over the guidelines below.
The planning parameters and urban design guidelines are:

Parameters
Building Form & Massing

Building Form

Requirements

The overall building form and massing of individual buildings is to consider how the building will be viewed, as well as impact views from major approaches, key open spaces and pedestrian malls.

The design of the building form and massing, together with the architectural treatment, is to consider the scale, form and architectural expression of the surrounding buildings, and be designed to create engaging and varied public spaces. Wall-like developments should be avoided.

Circular No: URA/PB/2019/18-CUDG

Parameters

Building Facades Requirements

The building façades of the development fronting all main roads and major public spaces are to be treated as main elevations.

The building facades of the development are to be well-articulated with solid (walls) / void (fenestration) areas that draw upon a combination of different materials (e.g. concrete, brick, steel, glass, greenery, etc.).

To create visual interest and to further break down the building mass, elements of tropical architecture such as sky terraces, balconies, sunshading louvers, deep recesses, window ledges, roof terraces, communal planter boxes and vertical green walls are to be provided as part of the development and integrated with the overall building form and architectural treatment of the development.

Relevant Circulars:  Sensitive Design and Development: An Industry Guide of Good
Practices to minimize Wall-Like Development

Building Height

Selected developments may be subject to site-specific building height controls, which will take precedence over technical height controls, whichever is lower.

Building Setback and Building Edge

Developments shall comply with the setback requirements in accordance with the prevailing Development Control guidelines. Selected developments may also be subject to site-specific setback controls, which will take precedence over prevailing DC guidelines.

Where applicable, developments are to be built up to the building setback line to create a well-defined urban streetscape. Up to 40% of the length of the building façade can be set back for articulation of the building form and skyrise greenery, or for the creation of open spaces.

Roofscape and Screening

The roof areas are to be considered as the “fifth” elevation and designed to complement the overall form, massing and architectural treatment of each development. The roofs can be designed to be usable outdoor spaces.

Screening Requirements

To ensure that the roof areas are well-designed and attractive when viewed from the surrounding developments, all service areas, mechanical and electrical (M&E) equipment, water tanks, etc., are to be located within and fully integrated into the building envelope and be visually wellscreened from the top and all sides of the development.

The performance requirements for the screening of roof-top services are as follows:

a) To be screened from the top and on all sides;

b) The spacing between the trellis or louver elements is to be equal to or less than their depth;

Circular No: URA/PB/2019/18-CUDG

Parameters

Requirements

c) The screening elements are to be orientated to cut off views from the street level and surrounding buildings.

Night Lighting

Good night lighting can enhance the nightscape and district character. The night lighting scheme should bring out the key architectural features of the building form, crown, facades, gardens and landscaped areas.

Signage

All developments shall comply with LTA’s signage and wayfinding requirements for Jurong Lake District, and submit the signage layout and design to the relevant Authorities for detailed evaluation and approval before Temporary Occupation Permit (TOP) can be issued.

Public Space
Appendix 2: Urban Design Plan – 1st Storey Pedestrian Network & Activity Generating Uses

It is important to provide public spaces within private developments for users to enjoy.
Selected developments are required to provide public spaces within the development site. These may be well-landscaped open spaces, or covered public spaces that provide a high degree of visual and physical porosity through the building.
Public spaces are to be publicly accessible at all times. They are to be connected to the key pedestrian routes at the 1st storey (such as open and covered walkways, through-block links, pedestrian malls and promenades), and, where applicable, designed to be well-integrated and easily accessible from the underground and elevated pedestrian networks within the development.

The design of these public spaces shall comply with the Design Guidelines for Privately Owned Public Spaces (POPS).

Relevant Circulars:  Design Guidelines and Good Practice Guide for Privately Owned
Public Spaces (POPS)

Uses at the 1st and 2nd Storey
Levels

To create vibrant precincts, as well as attractive and pedestrian-friendly streets, activity-generating uses (AGU) such as retail, food & beverage, and other active uses are to be provided at the following locations:

Appendix 2: Urban Design Plan – 1st Storey Pedestrian Network & Activity Generating Uses

 The 1st storey of developments fronting pedestrian malls, key streets and public spaces; and
 Alongside the elevated pedestrian walkways at the 2nd storey of the developments.
For more information on AGUs, please refer to the Development Control Handbook.

Outdoor Refreshment Areas

Where allowed, Outdoor Refreshment Areas (ORA), i.e. outdoor dining areas, can be considered within the public areas or open spaces within private development sites. The scale and design of the ORA and its structures (if any) are to complement the adjacent building. They can only

Circular No: URA/PB/2019/18-CUDG

Parameters

Requirements
be considered as an extension of an adjoining indoor F&B unit and are for seating only.

If provided, the Gross Floor Area (GFA) for the ORAs are to be computed as part of the maximum permissible GFA for the development and subject to the prevailing Development Control Guidelines under the Planning Act.

Developers are encouraged to incorporate spaces for ORAs at the design stage. The ORAs are to be clearly defined to prevent encroachment onto the adjacent pedestrian thoroughfares e.g. through the use of different floor finishes or planters, etc.

Pedestrian Network

JLD is planned as a pedestrian-friendly area with a comprehensive sheltered network of pedestrian malls, covered walkways, 2nd storey links, and through-block links. This network provides convenient, comfortable, and seamless connections between developments, transport facilities, key spaces and attractions, and ensures all-weather comfort.

Appendix 2: Urban Design Plan – 1st Storey Pedestrian Network & Activity Generating Uses

At-Grade Pedestrian Network
The at-grade pedestrian network is augmented by covered walkways that provide all-weather protected pedestrian routes. All developments are required to provide covered walkways at the 1st storey along the site boundaries / lines of Road Reserves or the designated setback lines. The covered walkways function as public amenities. They are to be kept free of obstruction at all times. In exchange, the area is exempted from GFA computation.

The minimum width of the covered walkways is to be 3.6m or 5m. Where colonnades are provided, the internal clear width of the covered walkways is to be minimum 3.0m and 4.4m respectively. To provide adequate protection for pedestrians during inclement weather, the external soffit heights are to minimally match the width of the covered walkway.

To maintain a distinct precinct character and to accentuate the urban character of JLD as a business district, all covered and open walkways within the development boundary of developments bounded by Jurong East Pedestrian Mall (J-Link), Jurong East MRT station and Jurong East Street 12, are to be predominantly paved in mid to dark grey granite slabs of minimally 600 by 600 mm.

Through-Block Links

Selected developments are required to provide through-block links to break down the scale and improve permeability of the streetblock.

Covered walkways and linkways, as well as through-block links may be exempted from GFA computation if they form part of the larger pedestrian network. Specific design requirements have been imposed on some key sites, depending on the locations of these through-block links.

Circular No: URA/PB/2019/18-CUDG

Parameters Appendix 3: UD Guide Plan – Elevated Pedestrian Network
Servicing, Vehicular Access & Car Parks
Greenery Replacement and Landscaping

Requirements Elevated Pedestrian Network (EPN)
The Elevated Pedestrian Network, also known as J-walk, is planned to provide seamless connectivity between developments and the existing Jurong East MRT interchange station. Building owners and developers are required to provide elevated links to connect between buildings.
The EPN is to match the finished floor level of the MRT station concourse (FFL 116.65) and be maintained at a constant level throughout its entire length, wherever possible.
The design and material specifications of floor finishes, hand rails, signage, street furniture and lighting shall be subject to the approval of URA and the relevant Competent Authorities. Detailed design of the signage, and the information displayed, shall also be subject to the approval of URA and the relevant Competent Authorities.
Vertical pedestrian circulation points are to be included within the building envelope to link the EPN to the covered walkways at the 1st storey. Each vertical circulation point is to include a pair of two- way escalators, staircases, and two passenger lifts. Unless otherwise specified, the entire EPN and the associated vertical circulation points are to remain open at all times and be visible from the at-grade and elevated pedestrian network.
General Conditions
The pedestrian network on all levels is to be designed for universal access. GFA exemption is applicable for public spaces, covered walkways, through-block links and elevated walkways, subject to the prevailing Development Control Guidelines.
All driveways and vehicular accesses are to be located away from public spaces or main pedestrian routes. This is to create a seamless and pedestrian-friendly network that is uninterrupted by vehicles.
To maintain an attractive streetscape, any above-grade car park and service areas, including refuse bin centre(s), loading / unloading bays and vehicle ingress/ egress, storage lane(s), and vehicular drop-offs/ lay-bys, etc. are to be fully integrated within the overall building form, and visually well-screened from above and on all sides. Electrical substation(s), where required, can be located at-grade but are not to front onto the main roads, pedestrian malls, or public spaces.
Sufficient holding bays for the vehicular access points to the car parks and service areas are to be provided within the development to ensure the smooth flow of vehicles along adjacent roads.
To create a green and sustainable city, all new developments will be required to incorporate landscaping in the form of sky terraces and roof gardens according to the Landscape Replacement Area (LRA) requirements. For more information, please refer to the Development Control Handbook.

Circular No: URA/PB/2019/18-CUDG

Parameters Smart, Green and Sustainable Initiatives
Works within the Road Reserves

Requirements In line with the planning vision of JLD, the adoption of appropriate infrastructure, design, technologies and programming is encouraged. These shall include, but are not limited to: place-making efforts to create a health and wellness district for the community; car-lite strategies such as provision of parking for bikes/ personal-mobility-devices and changing facilities to encourage active mobility; efficient freight delivery measures such as in-mall distribution; waste management measures to minimise wastage and encourage recycling; data collection as part of a proposed open digital platform for JLD; construction materials/methods that boost higher construction productivity, etc.
The developments shall incorporate energy-efficient, water efficient and environmentally-friendly design, technologies and practices, and shall be subject to the requirements of relevant authorities.
Open Walkway
As a guide, the open walkway within the Road Reserve is safeguarded for pedestrian use. Any proposed new paving with the Road Reserve will be subject to URA and LTA’s requirements and approval.
Tree and Shrub Planting Specifications
Any new tree or shrub planting specifications for the planting verge within the adjacent Road Reserves will be subject to URA and NParks’ requirements and approval.
Connection to Commuter Facilities
For developments with commuter facilities (e.g. bus stops and taxi stands) located in front of their buildings, sheltered linkways are to be provided between the covered walkways at the 1st storey to these facilities to provide direct continuous sheltered connections.
Dedicated Cycling Routes Certain key roads within Jurong Gateway will be earmarked as dedicated cycling routes (please refer to the Special Detailed Control Plan: Connectivity Plan). The alignment, width and design of the cycling routes and associated street furniture are to be coordinated with URA and LTA.

JURONG EAST

CENT RAL

STR EET 13

JURONG

EAST

JURONG

JURONG

TRAL

1 EAST
CE N
JURONG
TOWN HALL LINK

GATEWAY

EAST

WAY

GATE
ROAD
TOWN

JURONG

BOON

URO

J

NG

DRIVE

LAY

GATEWAY

EAST

STREET 21
WAY

JURONG

VEN TUR E

VENTURE
HALL

AVENUE DRIVE

EAST

INTER NATIO NAL

ROAD

JURONG

STREET 11

BUSIN ESS

TOH

GUAN

ROAD

PARK

APPENDIX 1 URBAN DESIGN GUIDELINES FOR JURONG GATEWAY (JURONG EAST PLANNING AREA) URBAN DESIGN PLAN
- BOUNDARY
LEGEND AREA WITH URBAN DESIGN GUIDELINES AND PLANS URBAN DESIGN AREA

SCALE
0.2 HA
DRWG NO DATE GROUP

: 1:4000 @A3

0

80 M

: UDW/2019/001 : OCT 2019 : AUDG

JURONG EAST

CENT RAL

STR EET 13

JURONG

EAST

JURONG

JURONG

TRAL

1 EAST
CE N
JURONG
TOWN HALL LINK

GATEWAY

I2 EAST

WAY

GATE
ROAD
TOWN
(69

JURONG

BOON

URO

J

NG

DRIVE

LAY

GATEWAY

EAST

STREET 21
WAY

JURONG

VEN TUR E

VENTURE
HALL

AVENUE DRIVE

EAST

INTER NATIO NAL

JURONG

ROAD

STREET 11

BUSIN ESS

TOH

GUAN

ROAD

PARK

APPENDIX 2 URBAN DESIGN GUIDELINES FOR JURONG GATEWAY (JURONG EAST PLANNING AREA)
URBAN DESIGN PLAN
- 1ST STOREY PEDESTRIAN NETWORK & ACTIVITY GENERATING USES

LEGEND AREA WITH URBAN DESIGN GUIDELINES AND PLANS

1

MONUMENT

COVERED WALKWAY/ COVERED LINKWAY

PARK/ OPEN SPACE

THROUGH-BLOCK LINK

PEDESTRIAN MALL/ PROMENADE/ PLAZA

ACTIVITY GENERATING USES

VERTICAL PEDESTRIAN CIRCULATION PUBLIC SPACE

NOTE: WHEN THERE IS NO INDICATION, ALL SHALL BE SUBJECTED TO PREVAILING GUIDELINES LIST OF GAZETTED NATIONAL MONUMENT
(69 JURONG TOWN HALL

SCALE

: 1:4000 @A3

0.2 HA

0

80 M

DRWG NO DATE GROUP

: UDW/2019/002 : OCT 2019 : AUDG